Author Question: When work is completed under the original estimate, the major problem is _____. a. material costs ... (Read 91 times)

maychende

  • Hero Member
  • *****
  • Posts: 556
When work is completed under the original estimate, the major problem is _____.
 
  a. material costs are not accurate
  b. poor historical data
  c. bids are not competitive
  d. profits are limited

Question 2

Determining probable construction costs are _____ estimates.
 
  a. pre-construction
  b. preliminary
  c. detailed
  d. resource



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Gabe

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

c

Answer to Question 2

a




maychende

  • Member
  • Posts: 556
Reply 2 on: Jul 24, 2018
Wow, this really help


yeungji

  • Member
  • Posts: 319
Reply 3 on: Yesterday
Excellent

 

Did you know?

The Centers for Disease Control and Prevention (CDC) was originally known as the Communicable Disease Center, which was formed to fight malaria. It was originally headquartered in Atlanta, Georgia, since the Southern states faced the worst threat from malaria.

Did you know?

This year, an estimated 1.4 million Americans will have a new or recurrent heart attack.

Did you know?

Pubic lice (crabs) are usually spread through sexual contact. You cannot catch them by using a public toilet.

Did you know?

Medication errors are more common among seriously ill patients than with those with minor conditions.

Did you know?

Complications of influenza include: bacterial pneumonia, ear and sinus infections, dehydration, and worsening of chronic conditions such as asthma, congestive heart failure, or diabetes.

For a complete list of videos, visit our video library