Author Question: Before a panel is tilted up, workers install beam seats and _____. a. panel connectors b. ... (Read 109 times)

Mr. Wonderful

  • Hero Member
  • *****
  • Posts: 866
Before a panel is tilted up, workers install beam seats and _____.
 
  a. panel connectors
  b. welding plates
  c. joists
  d. shelf angles

Question 2

During panel lifting and bracing, only the erection team is allowed in the _____.
 
  a. danger zone
  b. boom swing arc
  c. controlled-access zone
  d. lifting perimeter



kardosa007

  • Sr. Member
  • ****
  • Posts: 300
Answer to Question 1

d

Answer to Question 2

c



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Giardia is one of the most common intestinal parasites worldwide, and infects up to 20% of the world population, mostly in poorer countries with inadequate sanitation. Infections are most common in children, though chronic Giardia is more common in adults.

Did you know?

The most destructive flu epidemic of all times in recorded history occurred in 1918, with approximately 20 million deaths worldwide.

Did you know?

When blood is exposed to air, it clots. Heparin allows the blood to come in direct contact with air without clotting.

Did you know?

Most childhood vaccines are 90–99% effective in preventing disease. Side effects are rarely serious.

Did you know?

About 3.2 billion people, nearly half the world population, are at risk for malaria. In 2015, there are about 214 million malaria cases and an estimated 438,000 malaria deaths.

For a complete list of videos, visit our video library