Author Question: In steel erection, written authorization must notify the steel erection contractor that concrete ... (Read 69 times)

newbem

  • Hero Member
  • *****
  • Posts: 579
In steel erection, written authorization must notify the steel erection contractor that concrete used in footings has withered:
 
  A. Cured to at least 75 of its intended minimum compressive design strength.
  B. Has cured sufficiently to support the loads that will be imposed during erection.
  C. Both A and B.

Question 2

The purpose of ROPS is to keep the operator of the equipment in question from being crushed should the equipment roll over.
 
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

AaaA

  • Sr. Member
  • ****
  • Posts: 339
Answer to Question 1

C

Answer to Question 2

T



newbem

  • Hero Member
  • *****
  • Posts: 579
Both answers were spot on, thank you once again



AaaA

  • Sr. Member
  • ****
  • Posts: 339

 

Did you know?

Aspirin may benefit 11 different cancers, including those of the colon, pancreas, lungs, prostate, breasts, and leukemia.

Did you know?

Though newer “smart” infusion pumps are increasingly becoming more sophisticated, they cannot prevent all programming and administration errors. Health care professionals that use smart infusion pumps must still practice the rights of medication administration and have other professionals double-check all high-risk infusions.

Did you know?

Thyroid conditions may make getting pregnant impossible.

Did you know?

Amoebae are the simplest type of protozoans, and are characterized by a feeding and dividing trophozoite stage that moves by temporary extensions called pseudopodia or false feet.

Did you know?

Women are 50% to 75% more likely than men to experience an adverse drug reaction.

For a complete list of videos, visit our video library