Author Question: To calculate an activity's latest finish time, you should consider its a. predecessors' latest ... (Read 157 times)

pane00

  • Hero Member
  • *****
  • Posts: 579
To calculate an activity's latest finish time, you should consider its
 a. predecessors' latest finish times c. successors' earliest start times
  b. predecessors' latest start times d. successors' latest start times

Question 2

The equation that describes how the dependent variable (y) is related to the independent variable (x) is called _____.
 a. the correlation model
  b. the regression model
  c. correlation analysis
  d. None of the answers is correct.



matt95

  • Sr. Member
  • ****
  • Posts: 317
Answer to Question 1

D

Answer to Question 2

b



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Acetaminophen (Tylenol) in overdose can seriously damage the liver. It should never be taken by people who use alcohol heavily; it can result in severe liver damage and even a condition requiring a liver transplant.

Did you know?

Malaria was not eliminated in the United States until 1951. The term eliminated means that no new cases arise in a country for 3 years.

Did you know?

Pubic lice (crabs) are usually spread through sexual contact. You cannot catch them by using a public toilet.

Did you know?

Addicts to opiates often avoid treatment because they are afraid of withdrawal. Though unpleasant, with proper management, withdrawal is rarely fatal and passes relatively quickly.

Did you know?

There are approximately 3 million unintended pregnancies in the United States each year.

For a complete list of videos, visit our video library