Author Question: To calculate an activity's latest finish time, you should consider its a. predecessors' latest ... (Read 180 times)

pane00

  • Hero Member
  • *****
  • Posts: 579
To calculate an activity's latest finish time, you should consider its
 a. predecessors' latest finish times c. successors' earliest start times
  b. predecessors' latest start times d. successors' latest start times

Question 2

The equation that describes how the dependent variable (y) is related to the independent variable (x) is called _____.
 a. the correlation model
  b. the regression model
  c. correlation analysis
  d. None of the answers is correct.



matt95

  • Sr. Member
  • ****
  • Posts: 317
Answer to Question 1

D

Answer to Question 2

b



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Your heart beats over 36 million times a year.

Did you know?

Certain topical medications such as clotrimazole and betamethasone are not approved for use in children younger than 12 years of age. They must be used very cautiously, as directed by a doctor, to treat any child. Children have a much greater response to topical steroid medications.

Did you know?

Alzheimer's disease affects only about 10% of people older than 65 years of age. Most forms of decreased mental function and dementia are caused by disuse (letting the mind get lazy).

Did you know?

More than 150,000 Americans killed by cardiovascular disease are younger than the age of 65 years.

Did you know?

Approximately 70% of expectant mothers report experiencing some symptoms of morning sickness during the first trimester of pregnancy.

For a complete list of videos, visit our video library