Author Question: The longest path through a PERT diagram is called: A) slack time. B) the precedent activity ... (Read 92 times)

Jramos095

  • Hero Member
  • *****
  • Posts: 528
The longest path through a PERT diagram is called:
 
  A) slack time.
  B) the precedent activity path.
  C) maximum path time.
  D) the critical path.

Question 2

If the ERP vendor is a publicly traded firm it is useful to examine public reports to make sure they are in strong ________ position.
 
  A) managerial
  B) growth
  C) technical
  D) financial



daiying98

  • Sr. Member
  • ****
  • Posts: 354
Answer to Question 1

D

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Certain chemicals, after ingestion, can be converted by the body into cyanide. Most of these chemicals have been removed from the market, but some old nail polish remover, solvents, and plastics manufacturing solutions can contain these substances.

Did you know?

There are approximately 3 million unintended pregnancies in the United States each year.

Did you know?

Immunoglobulin injections may give short-term protection against, or reduce severity of certain diseases. They help people who have an inherited problem making their own antibodies, or those who are having certain types of cancer treatments.

Did you know?

If all the neurons in the human body were lined up, they would stretch more than 600 miles.

Did you know?

Amoebae are the simplest type of protozoans, and are characterized by a feeding and dividing trophozoite stage that moves by temporary extensions called pseudopodia or false feet.

For a complete list of videos, visit our video library