Author Question: The longest path through a PERT diagram is called: A) slack time. B) the precedent activity ... (Read 144 times)

Jramos095

  • Hero Member
  • *****
  • Posts: 528
The longest path through a PERT diagram is called:
 
  A) slack time.
  B) the precedent activity path.
  C) maximum path time.
  D) the critical path.

Question 2

If the ERP vendor is a publicly traded firm it is useful to examine public reports to make sure they are in strong ________ position.
 
  A) managerial
  B) growth
  C) technical
  D) financial



daiying98

  • Sr. Member
  • ****
  • Posts: 354
Answer to Question 1

D

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

There are more nerve cells in one human brain than there are stars in the Milky Way.

Did you know?

Common abbreviations that cause medication errors include U (unit), mg (milligram), QD (every day), SC (subcutaneous), TIW (three times per week), D/C (discharge or discontinue), HS (at bedtime or "hours of sleep"), cc (cubic centimeters), and AU (each ear).

Did you know?

The most common childhood diseases include croup, chickenpox, ear infections, flu, pneumonia, ringworm, respiratory syncytial virus, scabies, head lice, and asthma.

Did you know?

The cure for trichomoniasis is easy as long as the patient does not drink alcoholic beverages for 24 hours. Just a single dose of medication is needed to rid the body of the disease. However, without proper precautions, an individual may contract the disease repeatedly. In fact, most people develop trichomoniasis again within three months of their last treatment.

Did you know?

As of mid-2016, 18.2 million people were receiving advanced retroviral therapy (ART) worldwide. This represents between 43–50% of the 34–39.8 million people living with HIV.

For a complete list of videos, visit our video library