The longest path through a PERT diagram is called:
 
  A) slack time.
  B) the precedent activity path.
  C) maximum path time.
  D) the critical path.

Question 2

If the ERP vendor is a publicly traded firm it is useful to examine public reports to make sure they are in strong ________ position.
 
  A) managerial
  B) growth
  C) technical
  D) financial



daiying98

  • Sr. Member
  • ****
  • Posts: 354
Answer to Question 1

D

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The first monoclonal antibodies were made exclusively from mouse cells. Some are now fully human, which means they are likely to be safer and may be more effective than older monoclonal antibodies.

Did you know?

According to animal studies, the typical American diet is damaging to the liver and may result in allergies, low energy, digestive problems, and a lack of ability to detoxify harmful substances.

Did you know?

Acetaminophen (Tylenol) in overdose can seriously damage the liver. It should never be taken by people who use alcohol heavily; it can result in severe liver damage and even a condition requiring a liver transplant.

Did you know?

Only 12 hours after an egg cell is fertilized by a sperm cell, the egg cell starts to divide. As it continues to divide, it moves along the fallopian tube toward the uterus at about 1 inch per day.

Did you know?

To maintain good kidney function, you should drink at least 3 quarts of water daily. Water dilutes urine and helps prevent concentrations of salts and minerals that can lead to kidney stone formation. Chronic dehydration is a major contributor to the development of kidney stones.

For a complete list of videos, visit our video library