Author Question: Design/build means that a. One company is responsible for both design and construction b. ... (Read 86 times)

jilianpiloj

  • Hero Member
  • *****
  • Posts: 521
Design/build means that
 
  a. One company is responsible for both design and construction
  b. Construction begins before design is complete
  c. The project is technically complex
  d. Both A and B

Question 2

Which of the following is true of a GMP contract?
 
  a. GMP is the same as a lump sum bid
  b. The contractor passes all costs to the owner up to a predetermined maximum
  c. The owner assumes all project risk
  d. The construction manager assumes all project risk
  e. None of the above



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

ky860224

  • Sr. Member
  • ****
  • Posts: 350
Answer to Question 1

A

Answer to Question 2

B





 

Did you know?

Blood is approximately twice as thick as water because of the cells and other components found in it.

Did you know?

Patients should never assume they are being given the appropriate drugs. They should make sure they know which drugs are being prescribed, and always double-check that the drugs received match the prescription.

Did you know?

By definition, when a medication is administered intravenously, its bioavailability is 100%.

Did you know?

The use of salicylates dates back 2,500 years to Hippocrates's recommendation of willow bark (from which a salicylate is derived) as an aid to the pains of childbirth. However, overdosage of salicylates can harm body fluids, electrolytes, the CNS, the GI tract, the ears, the lungs, the blood, the liver, and the kidneys and cause coma or death.

Did you know?

Your chance of developing a kidney stone is 1 in 10. In recent years, approximately 3.7 million people in the United States were diagnosed with a kidney disease.

For a complete list of videos, visit our video library