Design/build means that
 
  a. One company is responsible for both design and construction
  b. Construction begins before design is complete
  c. The project is technically complex
  d. Both A and B

Question 2

Which of the following is true of a GMP contract?
 
  a. GMP is the same as a lump sum bid
  b. The contractor passes all costs to the owner up to a predetermined maximum
  c. The owner assumes all project risk
  d. The construction manager assumes all project risk
  e. None of the above



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

ky860224

  • Sr. Member
  • ****
  • Posts: 350
Answer to Question 1

A

Answer to Question 2

B





 

Did you know?

Giardia is one of the most common intestinal parasites worldwide, and infects up to 20% of the world population, mostly in poorer countries with inadequate sanitation. Infections are most common in children, though chronic Giardia is more common in adults.

Did you know?

In most cases, kidneys can recover from almost complete loss of function, such as in acute kidney (renal) failure.

Did you know?

Earwax has antimicrobial properties that reduce the viability of bacteria and fungus in the human ear.

Did you know?

Approximately 25% of all reported medication errors result from some kind of name confusion.

Did you know?

Many supplement containers do not even contain what their labels say. There are many documented reports of products containing much less, or more, that what is listed on their labels. They may also contain undisclosed prescription drugs and even contaminants.

For a complete list of videos, visit our video library