This topic contains a solution. Click here to go to the answer

Author Question: The latest finish time for an activity is the largest of the latest start times for all activities ... (Read 339 times)

nenivikky

  • Hero Member
  • *****
  • Posts: 516
The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity.
  Indicate whether the statement is true or false

Question 2

A descriptive measure that is computed from a sample is called a statistic.
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

shayla

  • Sr. Member
  • ****
  • Posts: 323
Answer to Question 1

F

Answer to Question 2

T




nenivikky

  • Member
  • Posts: 516
Reply 2 on: Jun 24, 2018
YES! Correct, THANKS for helping me on my review


pratush dev

  • Member
  • Posts: 321
Reply 3 on: Yesterday
Thanks for the timely response, appreciate it

 

Did you know?

On average, someone in the United States has a stroke about every 40 seconds. This is about 795,000 people per year.

Did you know?

Addicts to opiates often avoid treatment because they are afraid of withdrawal. Though unpleasant, with proper management, withdrawal is rarely fatal and passes relatively quickly.

Did you know?

It is believed that humans initially contracted crabs from gorillas about 3 million years ago from either sleeping in gorilla nests or eating the apes.

Did you know?

According to research, pregnant women tend to eat more if carrying a baby boy. Male fetuses may secrete a chemical that stimulates their mothers to step up her energy intake.

Did you know?

In 1885, the Lloyd Manufacturing Company of Albany, New York, promoted and sold "Cocaine Toothache Drops" at 15 cents per bottle! In 1914, the Harrison Narcotic Act brought the sale and distribution of this drug under federal control.

For a complete list of videos, visit our video library