Author Question: Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times ... (Read 153 times)

newyorker26

  • Hero Member
  • *****
  • Posts: 536
Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W
 a. is 10.
  b. is 12.
  c. is 15.
  d. cannot be determined.

Question 2

If we are testing for the equality of 3 population means, we should use the _____.
 a. test statistic F
  b. test statistic t
  c. test statistic z
  d. test statistic 2



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

tanna.moeller

  • Sr. Member
  • ****
  • Posts: 328
Answer to Question 1

C

Answer to Question 2

d





 

Did you know?

More than 150,000 Americans killed by cardiovascular disease are younger than the age of 65 years.

Did you know?

The most common treatment options for addiction include psychotherapy, support groups, and individual counseling.

Did you know?

Cyanide works by making the human body unable to use oxygen.

Did you know?

In 1864, the first barbiturate (barbituric acid) was synthesized.

Did you know?

Adult head lice are gray, about ? inch long, and often have a tiny dot on their backs. A female can lay between 50 and 150 eggs within the several weeks that she is alive. They feed on human blood.

For a complete list of videos, visit our video library