Author Question: Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times ... (Read 99 times)

newyorker26

  • Hero Member
  • *****
  • Posts: 536
Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W
 a. is 10.
  b. is 12.
  c. is 15.
  d. cannot be determined.

Question 2

If we are testing for the equality of 3 population means, we should use the _____.
 a. test statistic F
  b. test statistic t
  c. test statistic z
  d. test statistic 2



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

tanna.moeller

  • Sr. Member
  • ****
  • Posts: 328
Answer to Question 1

C

Answer to Question 2

d





 

Did you know?

The training of an anesthesiologist typically requires four years of college, 4 years of medical school, 1 year of internship, and 3 years of residency.

Did you know?

Acetaminophen (Tylenol) in overdose can seriously damage the liver. It should never be taken by people who use alcohol heavily; it can result in severe liver damage and even a condition requiring a liver transplant.

Did you know?

After a vasectomy, it takes about 12 ejaculations to clear out sperm that were already beyond the blocked area.

Did you know?

Fungal nail infections account for up to 30% of all skin infections. They affect 5% of the general population—mostly people over the age of 70.

Did you know?

The U.S. Pharmacopeia Medication Errors Reporting Program states that approximately 50% of all medication errors involve insulin.

For a complete list of videos, visit our video library