Author Question: The earliest start time rule a. compares the starting times of all activities for successors of an ... (Read 124 times)

sjones

  • Hero Member
  • *****
  • Posts: 520
The earliest start time rule
 a. compares the starting times of all activities for successors of an activity.
  b. compares the finish times for all immediate predecessors of an activity.
  c. determines when the project can begin.
  d. determines when the project must begin.

Question 2

In an analysis of variance, one estimate of is based upon the differences between the treatment means and the _____.
 a. means of each sample
  b. overall sample mean
  c. sum of observations
  d. populations have equal means



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

alexisweber49

  • Sr. Member
  • ****
  • Posts: 311
Answer to Question 1

B

Answer to Question 2

d




sjones

  • Member
  • Posts: 520
Reply 2 on: Jun 24, 2018
:D TYSM


Mochi

  • Member
  • Posts: 300
Reply 3 on: Yesterday
Excellent

 

Did you know?

A seasonal flu vaccine is the best way to reduce the chances you will get seasonal influenza and spread it to others.

Did you know?

Human stomach acid is strong enough to dissolve small pieces of metal such as razor blades or staples.

Did you know?

Excessive alcohol use costs the country approximately $235 billion every year.

Did you know?

Cyanide works by making the human body unable to use oxygen.

Did you know?

Warfarin was developed as a consequence of the study of a strange bleeding disorder that suddenly occurred in cattle on the northern prairies of the United States in the early 1900s.

For a complete list of videos, visit our video library