The earliest start time rule
 a. compares the starting times of all activities for successors of an activity.
  b. compares the finish times for all immediate predecessors of an activity.
  c. determines when the project can begin.
  d. determines when the project must begin.

Question 2

In an analysis of variance, one estimate of is based upon the differences between the treatment means and the _____.
 a. means of each sample
  b. overall sample mean
  c. sum of observations
  d. populations have equal means



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

alexisweber49

  • Sr. Member
  • ****
  • Posts: 311
Answer to Question 1

B

Answer to Question 2

d




sjones

  • Member
  • Posts: 520
Reply 2 on: Jun 24, 2018
Great answer, keep it coming :)


diana chang

  • Member
  • Posts: 288
Reply 3 on: Yesterday
Gracias!

 

Did you know?

No drugs are available to relieve parathyroid disease. Parathyroid disease is caused by a parathyroid tumor, and it needs to be removed by surgery.

Did you know?

Vital signs (blood pressure, temperature, pulse rate, respiration rate) should be taken before any drug administration. Patients should be informed not to use tobacco or caffeine at least 30 minutes before their appointment.

Did you know?

The U.S. Pharmacopeia Medication Errors Reporting Program states that approximately 50% of all medication errors involve insulin.

Did you know?

Approximately 15–25% of recognized pregnancies end in miscarriage. However, many miscarriages often occur before a woman even knows she is pregnant.

Did you know?

Women are 50% to 75% more likely than men to experience an adverse drug reaction.

For a complete list of videos, visit our video library