The earliest start time rule
a. compares the starting times of all activities for successors of an activity.
b. compares the finish times for all immediate predecessors of an activity.
c. determines when the project can begin.
d. determines when the project must begin.
Question 2
In an analysis of variance, one estimate of is based upon the differences between the treatment means and the _____.
a. means of each sample
b. overall sample mean
c. sum of observations
d. populations have equal means