Author Question: The longest path through a PERT diagram is called: A) slack time. B) the precedent activity ... (Read 147 times)

Jramos095

  • Hero Member
  • *****
  • Posts: 528
The longest path through a PERT diagram is called:
 
  A) slack time.
  B) the precedent activity path.
  C) maximum path time.
  D) the critical path.

Question 2

If the ERP vendor is a publicly traded firm it is useful to examine public reports to make sure they are in strong ________ position.
 
  A) managerial
  B) growth
  C) technical
  D) financial



daiying98

  • Sr. Member
  • ****
  • Posts: 354
Answer to Question 1

D

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The Centers for Disease Control and Prevention (CDC) was originally known as the Communicable Disease Center, which was formed to fight malaria. It was originally headquartered in Atlanta, Georgia, since the Southern states faced the worst threat from malaria.

Did you know?

As the western states of America were settled, pioneers often had to drink rancid water from ponds and other sources. This often resulted in chronic diarrhea, causing many cases of dehydration and death that could have been avoided if clean water had been available.

Did you know?

There are 20 feet of blood vessels in each square inch of human skin.

Did you know?

Less than one of every three adults with high LDL cholesterol has the condition under control. Only 48.1% with the condition are being treated for it.

Did you know?

Malaria was not eliminated in the United States until 1951. The term eliminated means that no new cases arise in a country for 3 years.

For a complete list of videos, visit our video library