Author Question: Evaluation of a contractor's construction schedule should be limited to which of the following ... (Read 166 times)

NguyenJ

  • Hero Member
  • *****
  • Posts: 516
Evaluation of a contractor's construction schedule should be limited to which of the following considerations?
 
  A. Date of Completion, Date of Award, Sequence of operations
   B. Date of Award, Network Logic, Sequence of Operations
   C. Completion Date, Network Logic, Beginning Date
   D. Date of Award, Date of Completion, Network Logic
   E. Sequence of Operations, Date of Completion, Date of Completion

Question 2

When you receive the contractor's monthly partial payment request on a unit-price project, the engineer or resident project representative should:
 
  A. just initial the form and forward it to the owner as no field review is necessary.
   B. reject it.
   C. check only the contractor's arithmetic on its payment request, while you eyeball estimate the amount of work completed to see if it appears to compare favorably with the contractor's claim.
   D. check all of the contractor's field quantities accurately, along with all materials delivered to the site, and the contractor's claims to percentages of the various parts of the work completed.
   E. check all of the contractor's field quantities within reasonable percentages of completion, along with all materials delivered to the site.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Bigfoot1984

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

C

Answer to Question 2

D



NguyenJ

  • Hero Member
  • *****
  • Posts: 516
Both answers were spot on, thank you once again




 

Did you know?

In 2006, a generic antinausea drug named ondansetron was approved. It is used to stop nausea and vomiting associated with surgery, chemotherapy, and radiation therapy.

Did you know?

Oxytocin is recommended only for pregnancies that have a medical reason for inducing labor (such as eclampsia) and is not recommended for elective procedures or for making the birthing process more convenient.

Did you know?

Autoimmune diseases occur when the immune system destroys its own healthy tissues. When this occurs, white blood cells cannot distinguish between pathogens and normal cells.

Did you know?

To maintain good kidney function, you should drink at least 3 quarts of water daily. Water dilutes urine and helps prevent concentrations of salts and minerals that can lead to kidney stone formation. Chronic dehydration is a major contributor to the development of kidney stones.

Did you know?

Malaria was not eliminated in the United States until 1951. The term eliminated means that no new cases arise in a country for 3 years.

For a complete list of videos, visit our video library