Author Question: Evaluation of a contractor's construction schedule should be limited to which of the following ... (Read 173 times)

NguyenJ

  • Hero Member
  • *****
  • Posts: 516
Evaluation of a contractor's construction schedule should be limited to which of the following considerations?
 
  A. Date of Completion, Date of Award, Sequence of operations
   B. Date of Award, Network Logic, Sequence of Operations
   C. Completion Date, Network Logic, Beginning Date
   D. Date of Award, Date of Completion, Network Logic
   E. Sequence of Operations, Date of Completion, Date of Completion

Question 2

When you receive the contractor's monthly partial payment request on a unit-price project, the engineer or resident project representative should:
 
  A. just initial the form and forward it to the owner as no field review is necessary.
   B. reject it.
   C. check only the contractor's arithmetic on its payment request, while you eyeball estimate the amount of work completed to see if it appears to compare favorably with the contractor's claim.
   D. check all of the contractor's field quantities accurately, along with all materials delivered to the site, and the contractor's claims to percentages of the various parts of the work completed.
   E. check all of the contractor's field quantities within reasonable percentages of completion, along with all materials delivered to the site.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Bigfoot1984

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

C

Answer to Question 2

D



NguyenJ

  • Hero Member
  • *****
  • Posts: 516
Both answers were spot on, thank you once again




 

Did you know?

All adverse reactions are commonly charted in red ink in the patient's record and usually are noted on the front of the chart. Failure to follow correct documentation procedures may result in malpractice lawsuits.

Did you know?

Most fungi that pathogenically affect humans live in soil. If a person is not healthy, has an open wound, or is immunocompromised, a fungal infection can be very aggressive.

Did you know?

GI conditions that will keep you out of the U.S. armed services include ulcers, varices, fistulas, esophagitis, gastritis, congenital abnormalities, inflammatory bowel disease, enteritis, colitis, proctitis, duodenal diverticula, malabsorption syndromes, hepatitis, cirrhosis, cysts, abscesses, pancreatitis, polyps, certain hemorrhoids, splenomegaly, hernias, recent abdominal surgery, GI bypass or stomach stapling, and artificial GI openings.

Did you know?

Adult head lice are gray, about ? inch long, and often have a tiny dot on their backs. A female can lay between 50 and 150 eggs within the several weeks that she is alive. They feed on human blood.

Did you know?

Atropine was named after the Greek goddess Atropos, the oldest and ugliest of the three sisters known as the Fates, who controlled the destiny of men.

For a complete list of videos, visit our video library