Author Question: When the owner and the construction contractor agree to a predetermined price that cannot be ... (Read 70 times)

savannahhooper

  • Hero Member
  • *****
  • Posts: 576
When the owner and the construction contractor agree to a predetermined price that cannot be exceeded for the construction work, but will both share in any savings generated by the work being completed a price that is lower than the predetermined price; the contract format is known as ___________________ ______ contract.
 
  A. maximum guaranteed price
  B. incentive and penalty
  C. cost plus fixed fee
  D. unit price

Question 2

A set of construction documents that show how the construction was actually performed are known by the name ___________________ __.
 
  A. as-built drawings
  B. presentation drawings
  C. commissioning drawings
  D. none of the above



ASDFGJLO

  • Sr. Member
  • ****
  • Posts: 335
Answer to Question 1

A

Answer to Question 2

A



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

Adolescents often feel clumsy during puberty because during this time of development, their hands and feet grow faster than their arms and legs do. The body is therefore out of proportion. One out of five adolescents actually experiences growing pains during this period.

Did you know?

Thyroid conditions cause a higher risk of fibromyalgia and chronic fatigue syndrome.

Did you know?

Disorders that may affect pharmacodynamics include genetic mutations, malnutrition, thyrotoxicosis, myasthenia gravis, Parkinson's disease, and certain forms of insulin-resistant diabetes mellitus.

Did you know?

The familiar sounds of your heart are made by the heart's valves as they open and close.

Did you know?

On average, the stomach produces 2 L of hydrochloric acid per day.

For a complete list of videos, visit our video library