When the owner and the construction contractor agree to a predetermined price that cannot be exceeded for the construction work, but will both share in any savings generated by the work being completed a price that is lower than the predetermined price; the contract format is known as ___________________ ______ contract.
 
  A. maximum guaranteed price
  B. incentive and penalty
  C. cost plus fixed fee
  D. unit price

Question 2

A set of construction documents that show how the construction was actually performed are known by the name ___________________ __.
 
  A. as-built drawings
  B. presentation drawings
  C. commissioning drawings
  D. none of the above



ASDFGJLO

  • Sr. Member
  • ****
  • Posts: 335
Answer to Question 1

A

Answer to Question 2

A



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

Critical care patients are twice as likely to receive the wrong medication. Of these errors, 20% are life-threatening, and 42% require additional life-sustaining treatments.

Did you know?

Serum cholesterol testing in adults is recommended every 1 to 5 years. People with diabetes and a family history of high cholesterol should be tested even more frequently.

Did you know?

This year, an estimated 1.4 million Americans will have a new or recurrent heart attack.

Did you know?

Sildenafil (Viagra®) has two actions that may be of consequence in patients with heart disease. It can lower the blood pressure, and it can interact with nitrates. It should never be used in patients who are taking nitrates.

Did you know?

Approximately 500,000 babies are born each year in the United States to teenage mothers.

For a complete list of videos, visit our video library