Design/build means that
 
  a. One company is responsible for both design and construction
  b. Construction begins before design is complete
  c. The project is technically complex
  d. Both A and B

Question 2

Which of the following is true of a GMP contract?
 
  a. GMP is the same as a lump sum bid
  b. The contractor passes all costs to the owner up to a predetermined maximum
  c. The owner assumes all project risk
  d. The construction manager assumes all project risk
  e. None of the above



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

ky860224

  • Sr. Member
  • ****
  • Posts: 350
Answer to Question 1

A

Answer to Question 2

B





 

Did you know?

Individuals are never “cured” of addictions. Instead, they learn how to manage their disease to lead healthy, balanced lives.

Did you know?

Bacteria have been found alive in a lake buried one half mile under ice in Antarctica.

Did you know?

As of mid-2016, 18.2 million people were receiving advanced retroviral therapy (ART) worldwide. This represents between 43–50% of the 34–39.8 million people living with HIV.

Did you know?

Side effects from substance abuse include nausea, dehydration, reduced productivitiy, and dependence. Though these effects usually worsen over time, the constant need for the substance often overcomes rational thinking.

Did you know?

Oxytocin is recommended only for pregnancies that have a medical reason for inducing labor (such as eclampsia) and is not recommended for elective procedures or for making the birthing process more convenient.

For a complete list of videos, visit our video library