Which of the project types listed would most frequently use a construction management arrangement?
 
  a. Building construction
  b. Heavy construction
  c. Industrial
  d. Residential

Question 2

Owner involvement is highest during what project phase?
 
  a. Construction
  b. Engineering and design
  c. Concept and feasibility
  d. None of the above



courtney_bruh

  • Sr. Member
  • ****
  • Posts: 308
Answer to Question 1

A

Answer to Question 2

C



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

nelaaney

  • Hero Member
  • *****
  • Posts: 560
Both answers were spot on, thank you once again




 

Did you know?

Human neurons are so small that they require a microscope in order to be seen. However, some neurons can be up to 3 feet long, such as those that extend from the spinal cord to the toes.

Did you know?

Russia has the highest death rate from cardiovascular disease followed by the Ukraine, Romania, Hungary, and Poland.

Did you know?

Hip fractures are the most serious consequences of osteoporosis. The incidence of hip fractures increases with each decade among patients in their 60s to patients in their 90s for both women and men of all populations. Men and women older than 80 years of age show the highest incidence of hip fractures.

Did you know?

Vital signs (blood pressure, temperature, pulse rate, respiration rate) should be taken before any drug administration. Patients should be informed not to use tobacco or caffeine at least 30 minutes before their appointment.

Did you know?

Intradermal injections are somewhat difficult to correctly administer because the skin layers are so thin that it is easy to accidentally punch through to the deeper subcutaneous layer.

For a complete list of videos, visit our video library