This topic contains a solution. Click here to go to the answer

Author Question: _______________________ is/are great way(s) to uncover important aspects of a project . A. SWOT ... (Read 109 times)

nmorano1

  • Hero Member
  • *****
  • Posts: 598
___________________ ____ is/are great way(s) to uncover important aspects of a project .
 
  A. SWOT Analysis
  B. Brainstorming
  C. Mind Maps
  D. Both B and C

Question 2

What types of projects tend to be scheduled in terms of working days? Why?
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

bubulittle310@msn.cn

  • Sr. Member
  • ****
  • Posts: 281
Answer to Question 1

D

Answer to Question 2

Projects that are most susceptible to the elements (namely the weather) tend to
be scheduled in terms of working days. Examples would generally include the
construction of engineering projects (those specifically including the services of an
engineer but not an architect) such as highways, bridges, dams, airport runways, canals,
and utility installations. The specific durations of projects conducted in the elements are
difficult to quantify in calendar days. Rainfall at the very beginning of a project can stall
the entire work effort. In fact, large amounts of rainfall at any time during the
construction of engineering projects will generally have a significant impact on the
construction effort. This problem can be best addressed by defining construction duration
in terms of working days. This is regarded as the most equitable way to define duration
when weather can hamper progress. The use of working days permits the duration to be
defined in terms that are fair to the contractor. If calendar days were used to define
duration on such projects, the owner would be faced with numerous requests for time
extensions. Requesting time extensions can be adversarial and this would occur far too
often on engineering projects defined in calendar days.

On the other hand, building projects are generally only severely impacted by adverse
weather in the early stages of construction. In some regions of the country, building
projects are begun in the spring months when weather conditions are most conducive to
construction work. Once a building is dried in, the elements can still compromise the
work effort, but progress can generally still be made.




nmorano1

  • Member
  • Posts: 598
Reply 2 on: Jul 26, 2018
YES! Correct, THANKS for helping me on my review


flexer1n1

  • Member
  • Posts: 373
Reply 3 on: Yesterday
Thanks for the timely response, appreciate it

 

Did you know?

Pubic lice (crabs) are usually spread through sexual contact. You cannot catch them by using a public toilet.

Did you know?

Opium has influenced much of the world's most popular literature. The following authors were all opium users, of varying degrees: Lewis Carroll, Charles, Dickens, Arthur Conan Doyle, and Oscar Wilde.

Did you know?

There are immediate benefits of chiropractic adjustments that are visible via magnetic resonance imaging (MRI). It shows that spinal manipulation therapy is effective in decreasing pain and increasing the gaps between the vertebrae, reducing pressure that leads to pain.

Did you know?

The use of salicylates dates back 2,500 years to Hippocrates's recommendation of willow bark (from which a salicylate is derived) as an aid to the pains of childbirth. However, overdosage of salicylates can harm body fluids, electrolytes, the CNS, the GI tract, the ears, the lungs, the blood, the liver, and the kidneys and cause coma or death.

Did you know?

ACTH levels are normally highest in the early morning (between 6 and 8 A.M.) and lowest in the evening (between 6 and 11 P.M.). Therefore, a doctor who suspects abnormal levels looks for low ACTH in the morning and high ACTH in the evening.

For a complete list of videos, visit our video library