___________________ ____ is/are great way(s) to uncover important aspects of a project .
 
  A. SWOT Analysis
  B. Brainstorming
  C. Mind Maps
  D. Both B and C

Question 2

What types of projects tend to be scheduled in terms of working days? Why?
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

bubulittle310@msn.cn

  • Sr. Member
  • ****
  • Posts: 281
Answer to Question 1

D

Answer to Question 2

Projects that are most susceptible to the elements (namely the weather) tend to
be scheduled in terms of working days. Examples would generally include the
construction of engineering projects (those specifically including the services of an
engineer but not an architect) such as highways, bridges, dams, airport runways, canals,
and utility installations. The specific durations of projects conducted in the elements are
difficult to quantify in calendar days. Rainfall at the very beginning of a project can stall
the entire work effort. In fact, large amounts of rainfall at any time during the
construction of engineering projects will generally have a significant impact on the
construction effort. This problem can be best addressed by defining construction duration
in terms of working days. This is regarded as the most equitable way to define duration
when weather can hamper progress. The use of working days permits the duration to be
defined in terms that are fair to the contractor. If calendar days were used to define
duration on such projects, the owner would be faced with numerous requests for time
extensions. Requesting time extensions can be adversarial and this would occur far too
often on engineering projects defined in calendar days.

On the other hand, building projects are generally only severely impacted by adverse
weather in the early stages of construction. In some regions of the country, building
projects are begun in the spring months when weather conditions are most conducive to
construction work. Once a building is dried in, the elements can still compromise the
work effort, but progress can generally still be made.




nmorano1

  • Member
  • Posts: 598
Reply 2 on: Jul 26, 2018
Gracias!


komodo7

  • Member
  • Posts: 322
Reply 3 on: Yesterday
Thanks for the timely response, appreciate it

 

Did you know?

There are immediate benefits of chiropractic adjustments that are visible via magnetic resonance imaging (MRI). It shows that spinal manipulation therapy is effective in decreasing pain and increasing the gaps between the vertebrae, reducing pressure that leads to pain.

Did you know?

Vaccines cause herd immunity. If the majority of people in a community have been vaccinated against a disease, an unvaccinated person is less likely to get the disease since others are less likely to become sick from it and spread the disease.

Did you know?

It is widely believed that giving a daily oral dose of aspirin to heart attack patients improves their chances of survival because the aspirin blocks the formation of new blood clots.

Did you know?

About 100 new prescription or over-the-counter drugs come into the U.S. market every year.

Did you know?

The liver is the only organ that has the ability to regenerate itself after certain types of damage. As much as 25% of the liver can be removed, and it will still regenerate back to its original shape and size. However, the liver cannot regenerate after severe damage caused by alcohol.

For a complete list of videos, visit our video library