Author Question: To the contractor, what is the significance of the difference between an avoidable delay and an ... (Read 29 times)

maychende

  • Hero Member
  • *****
  • Posts: 556
To the contractor, what is the significance of the difference between an avoidable delay and an unavoidable delay?
 
  What will be an ideal response?

Question 2

What defines the start date and what defines the finish date of a contract, with the bracketed time being the project duration?
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

joshraies

  • Sr. Member
  • ****
  • Posts: 351
Answer to Question 1

An unavoidable delay is one for which the contractor can have some confidence
of receiving a time extension and possibly monetary compensation. The contract
documents will generally provide some guidance as to the appropriate procedures that are
to be followed to permit some relief for the contractor when unavoidable delays occur.
An avoidable delay,. on the other hand, implies that the contractor was or should have
been in control of circumstances and could have taken appropriate actions so the delay in
question would never have occurred. The contractor should have no expectation of
receiving a time extension or any damages for avoidable delays.

Answer to Question 2

The start date is generally specifically noted in the Notice to Proceed. The start
date may be specifically given or it may be stated in terms of the date of the Notice to
Proceed, e. g., ten days from the date of receipt of the notice to proceed. In some
contracts, the start date is the day the notice to proceed is received by the contractor.

The finish date of a contract (defining when no liquidated damages will be assessed
against the contractor) generally occurs at the point of substantial completion. Substantial
completion is the point in a project at which the owner is able to occupy the facility being
constructed and use it for its intended purpose. Only minor items of work may remain at
the time of substantial completion. These deficiencies are commonly itemized in the
punch list.




maychende

  • Member
  • Posts: 556
Reply 2 on: Jul 26, 2018
Great answer, keep it coming :)


olderstudent

  • Member
  • Posts: 339
Reply 3 on: Yesterday
Wow, this really help

 

Did you know?

In 1844, Charles Goodyear obtained the first patent for a rubber condom.

Did you know?

Aspirin is the most widely used drug in the world. It has even been recognized as such by the Guinness Book of World Records.

Did you know?

If you could remove all of your skin, it would weigh up to 5 pounds.

Did you know?

HIV testing reach is still limited. An estimated 40% of people with HIV (more than 14 million) remain undiagnosed and do not know their infection status.

Did you know?

Barbituric acid, the base material of barbiturates, was first synthesized in 1863 by Adolph von Bayer. His company later went on to synthesize aspirin for the first time, and Bayer aspirin is still a popular brand today.

For a complete list of videos, visit our video library