This topic contains a solution. Click here to go to the answer

Author Question: To the contractor, what is the significance of the difference between an avoidable delay and an ... (Read 41 times)

maychende

  • Hero Member
  • *****
  • Posts: 556
To the contractor, what is the significance of the difference between an avoidable delay and an unavoidable delay?
 
  What will be an ideal response?

Question 2

What defines the start date and what defines the finish date of a contract, with the bracketed time being the project duration?
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

joshraies

  • Sr. Member
  • ****
  • Posts: 351
Answer to Question 1

An unavoidable delay is one for which the contractor can have some confidence
of receiving a time extension and possibly monetary compensation. The contract
documents will generally provide some guidance as to the appropriate procedures that are
to be followed to permit some relief for the contractor when unavoidable delays occur.
An avoidable delay,. on the other hand, implies that the contractor was or should have
been in control of circumstances and could have taken appropriate actions so the delay in
question would never have occurred. The contractor should have no expectation of
receiving a time extension or any damages for avoidable delays.

Answer to Question 2

The start date is generally specifically noted in the Notice to Proceed. The start
date may be specifically given or it may be stated in terms of the date of the Notice to
Proceed, e. g., ten days from the date of receipt of the notice to proceed. In some
contracts, the start date is the day the notice to proceed is received by the contractor.

The finish date of a contract (defining when no liquidated damages will be assessed
against the contractor) generally occurs at the point of substantial completion. Substantial
completion is the point in a project at which the owner is able to occupy the facility being
constructed and use it for its intended purpose. Only minor items of work may remain at
the time of substantial completion. These deficiencies are commonly itemized in the
punch list.




maychende

  • Member
  • Posts: 556
Reply 2 on: Jul 26, 2018
Great answer, keep it coming :)


lindahyatt42

  • Member
  • Posts: 322
Reply 3 on: Yesterday
Gracias!

 

Did you know?

Inotropic therapy does not have a role in the treatment of most heart failure patients. These drugs can make patients feel and function better but usually do not lengthen the predicted length of their lives.

Did you know?

The human body's pharmacokinetics are quite varied. Our hair holds onto drugs longer than our urine, blood, or saliva. For example, alcohol can be detected in the hair for up to 90 days after it was consumed. The same is true for marijuana, cocaine, ecstasy, heroin, methamphetamine, and nicotine.

Did you know?

Women are 50% to 75% more likely than men to experience an adverse drug reaction.

Did you know?

Human stomach acid is strong enough to dissolve small pieces of metal such as razor blades or staples.

Did you know?

It is believed that the Incas used anesthesia. Evidence supports the theory that shamans chewed cocoa leaves and drilled holes into the heads of patients (letting evil spirits escape), spitting into the wounds they made. The mixture of cocaine, saliva, and resin numbed the site enough to allow hours of drilling.

For a complete list of videos, visit our video library