This topic contains a solution. Click here to go to the answer

Author Question: To the contractor, what is the significance of the difference between an avoidable delay and an ... (Read 40 times)

maychende

  • Hero Member
  • *****
  • Posts: 556
To the contractor, what is the significance of the difference between an avoidable delay and an unavoidable delay?
 
  What will be an ideal response?

Question 2

What defines the start date and what defines the finish date of a contract, with the bracketed time being the project duration?
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

joshraies

  • Sr. Member
  • ****
  • Posts: 351
Answer to Question 1

An unavoidable delay is one for which the contractor can have some confidence
of receiving a time extension and possibly monetary compensation. The contract
documents will generally provide some guidance as to the appropriate procedures that are
to be followed to permit some relief for the contractor when unavoidable delays occur.
An avoidable delay,. on the other hand, implies that the contractor was or should have
been in control of circumstances and could have taken appropriate actions so the delay in
question would never have occurred. The contractor should have no expectation of
receiving a time extension or any damages for avoidable delays.

Answer to Question 2

The start date is generally specifically noted in the Notice to Proceed. The start
date may be specifically given or it may be stated in terms of the date of the Notice to
Proceed, e. g., ten days from the date of receipt of the notice to proceed. In some
contracts, the start date is the day the notice to proceed is received by the contractor.

The finish date of a contract (defining when no liquidated damages will be assessed
against the contractor) generally occurs at the point of substantial completion. Substantial
completion is the point in a project at which the owner is able to occupy the facility being
constructed and use it for its intended purpose. Only minor items of work may remain at
the time of substantial completion. These deficiencies are commonly itemized in the
punch list.




maychende

  • Member
  • Posts: 556
Reply 2 on: Jul 26, 2018
Excellent


parshano

  • Member
  • Posts: 333
Reply 3 on: Yesterday
Gracias!

 

Did you know?

It is widely believed that giving a daily oral dose of aspirin to heart attack patients improves their chances of survival because the aspirin blocks the formation of new blood clots.

Did you know?

Cutaneous mucormycosis is a rare fungal infection that has been fatal in at least 29% of cases, and in as many as 83% of cases, depending on the patient's health prior to infection. It has occurred often after natural disasters such as tornados, and early treatment is essential.

Did you know?

Drug-induced pharmacodynamic effects manifested in older adults include drug-induced renal toxicity, which can be a major factor when these adults are experiencing other kidney problems.

Did you know?

Though the United States has largely rejected the metric system, it is used for currency, as in 100 pennies = 1 dollar. Previously, the British currency system was used, with measurements such as 12 pence to the shilling, and 20 shillings to the pound.

Did you know?

Malaria was not eliminated in the United States until 1951. The term eliminated means that no new cases arise in a country for 3 years.

For a complete list of videos, visit our video library