This topic contains a solution. Click here to go to the answer

Author Question: To the contractor, what is the significance of the difference between an avoidable delay and an ... (Read 8 times)

maychende

  • Hero Member
  • *****
  • Posts: 556
To the contractor, what is the significance of the difference between an avoidable delay and an unavoidable delay?
 
  What will be an ideal response?

Question 2

What defines the start date and what defines the finish date of a contract, with the bracketed time being the project duration?
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

joshraies

  • Sr. Member
  • ****
  • Posts: 351
Answer to Question 1

An unavoidable delay is one for which the contractor can have some confidence
of receiving a time extension and possibly monetary compensation. The contract
documents will generally provide some guidance as to the appropriate procedures that are
to be followed to permit some relief for the contractor when unavoidable delays occur.
An avoidable delay,. on the other hand, implies that the contractor was or should have
been in control of circumstances and could have taken appropriate actions so the delay in
question would never have occurred. The contractor should have no expectation of
receiving a time extension or any damages for avoidable delays.

Answer to Question 2

The start date is generally specifically noted in the Notice to Proceed. The start
date may be specifically given or it may be stated in terms of the date of the Notice to
Proceed, e. g., ten days from the date of receipt of the notice to proceed. In some
contracts, the start date is the day the notice to proceed is received by the contractor.

The finish date of a contract (defining when no liquidated damages will be assessed
against the contractor) generally occurs at the point of substantial completion. Substantial
completion is the point in a project at which the owner is able to occupy the facility being
constructed and use it for its intended purpose. Only minor items of work may remain at
the time of substantial completion. These deficiencies are commonly itemized in the
punch list.




maychende

  • Member
  • Posts: 556
Reply 2 on: Jul 26, 2018
Wow, this really help


Viet Thy

  • Member
  • Posts: 329
Reply 3 on: Yesterday
Excellent

 

Did you know?

The liver is the only organ that has the ability to regenerate itself after certain types of damage. As much as 25% of the liver can be removed, and it will still regenerate back to its original shape and size. However, the liver cannot regenerate after severe damage caused by alcohol.

Did you know?

Your skin wrinkles if you stay in the bathtub a long time because the outermost layer of skin (which consists of dead keratin) swells when it absorbs water. It is tightly attached to the skin below it, so it compensates for the increased area by wrinkling. This happens to the hands and feet because they have the thickest layer of dead keratin cells.

Did you know?

Addicts to opiates often avoid treatment because they are afraid of withdrawal. Though unpleasant, with proper management, withdrawal is rarely fatal and passes relatively quickly.

Did you know?

Medication errors are more common among seriously ill patients than with those with minor conditions.

Did you know?

In 2006, a generic antinausea drug named ondansetron was approved. It is used to stop nausea and vomiting associated with surgery, chemotherapy, and radiation therapy.

For a complete list of videos, visit our video library