Author Question: Which is not a significant challenge of project scheduling? a. deadlines exist. b. activities are ... (Read 82 times)

Pineapplelove6

  • Hero Member
  • *****
  • Posts: 560
Which is not a significant challenge of project scheduling?
 a. deadlines exist.
  b. activities are independent.
  c. many employees could be required.
  d. delays are costly.

Question 2

The critical F value with 8 numerator and 29 denominator degrees of freedom at  = .01 is _____.
 a. 2.28
  b. 3.20
  c. 3.33
  d. 3.64



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

kxciann

  • Sr. Member
  • ****
  • Posts: 356
Answer to Question 1

B

Answer to Question 2

b




Pineapplelove6

  • Member
  • Posts: 560
Reply 2 on: Jun 24, 2018
Great answer, keep it coming :)


Zebsrer

  • Member
  • Posts: 284
Reply 3 on: Yesterday
Thanks for the timely response, appreciate it

 

Did you know?

Essential fatty acids have been shown to be effective against ulcers, asthma, dental cavities, and skin disorders such as acne.

Did you know?

Addicts to opiates often avoid treatment because they are afraid of withdrawal. Though unpleasant, with proper management, withdrawal is rarely fatal and passes relatively quickly.

Did you know?

Nitroglycerin is used to alleviate various heart-related conditions, and it is also the chief component of dynamite (but mixed in a solid clay base to stabilize it).

Did you know?

The National Institutes of Health have supported research into acupuncture. This has shown that acupuncture significantly reduced pain associated with osteoarthritis of the knee, when used as a complement to conventional therapies.

Did you know?

As of mid-2016, 18.2 million people were receiving advanced retroviral therapy (ART) worldwide. This represents between 43–50% of the 34–39.8 million people living with HIV.

For a complete list of videos, visit our video library