Question 2

The biggest challenge in planning large-scale systems development is scheduling. Describethe three approaches that organizations can take to address this challenge.
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

voltaire123

  • Sr. Member
  • ****
  • Posts: 301
Answer to Question 1

TRUE

Answer to Question 2

The first approach that organizations can take to address the challenge of scheduling
large-scale systems development projects is to avoid all major schedule risks by never
developing software in-house. Instead, they can license software from vendors. However, if no
suitable software exists, companies can take one of two remaining approaches. They can admit
the impossibility of systems development scheduling and plan accordingly. They can abandon
the systems development life cycle and decide to invest a certain level of resources into a project,
manage it as best as they can, and take the schedule that produces results. The third approach is
to attempt to schedule the development project in spite of all difficulties. Several different
estimation techniques can be used. If the project is similar to a past project, the schedule data
from that past project can be used for planning. When such similar past projects exist, this
technique can produce quality schedule estimates. If there is no such past project, managers can
estimate the number of lines of code that will need to be written. Then they can use industry or
company averages to estimate the time required. Another technique is to estimate the function
points in a program, use each function point to determine the number of lines of code, and use
that number to estimate schedules.




sheilaspns

  • Member
  • Posts: 567
Reply 2 on: Jul 7, 2018
Great answer, keep it coming :)


ryhom

  • Member
  • Posts: 366
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

Famous people who died from poisoning or drug overdose include, Adolf Hitler, Socrates, Juan Ponce de Leon, Marilyn Monroe, Judy Garland, and John Belushi.

Did you know?

Most fungi that pathogenically affect humans live in soil. If a person is not healthy, has an open wound, or is immunocompromised, a fungal infection can be very aggressive.

Did you know?

Women are two-thirds more likely than men to develop irritable bowel syndrome. This may be attributable to hormonal changes related to their menstrual cycles.

Did you know?

Hypertension is a silent killer because it is deadly and has no significant early symptoms. The danger from hypertension is the extra load on the heart, which can lead to hypertensive heart disease and kidney damage. This occurs without any major symptoms until the high blood pressure becomes extreme. Regular blood pressure checks are an important method of catching hypertension before it can kill you.

Did you know?

A serious new warning has been established for pregnant women against taking ACE inhibitors during pregnancy. In the study, the risk of major birth defects in children whose mothers took ACE inhibitors during the first trimester was nearly three times higher than in children whose mothers didn't take ACE inhibitors. Physicians can prescribe alternative medications for pregnant women who have symptoms of high blood pressure.

For a complete list of videos, visit our video library