The biggest challenge in planning large-scale systems development is scheduling. Describethe three approaches that organizations can take to address this challenge.
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

voltaire123

  • Sr. Member
  • ****
  • Posts: 301
Answer to Question 1

TRUE

Answer to Question 2

The first approach that organizations can take to address the challenge of scheduling
large-scale systems development projects is to avoid all major schedule risks by never
developing software in-house. Instead, they can license software from vendors. However, if no
suitable software exists, companies can take one of two remaining approaches. They can admit
the impossibility of systems development scheduling and plan accordingly. They can abandon
the systems development life cycle and decide to invest a certain level of resources into a project,
manage it as best as they can, and take the schedule that produces results. The third approach is
to attempt to schedule the development project in spite of all difficulties. Several different
estimation techniques can be used. If the project is similar to a past project, the schedule data
from that past project can be used for planning. When such similar past projects exist, this
technique can produce quality schedule estimates. If there is no such past project, managers can
estimate the number of lines of code that will need to be written. Then they can use industry or
company averages to estimate the time required. Another technique is to estimate the function
points in a program, use each function point to determine the number of lines of code, and use
that number to estimate schedules.




sheilaspns

  • Member
  • Posts: 567
Reply 2 on: Jul 7, 2018
YES! Correct, THANKS for helping me on my review


Laurenleakan

  • Member
  • Posts: 309
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

Vital signs (blood pressure, temperature, pulse rate, respiration rate) should be taken before any drug administration. Patients should be informed not to use tobacco or caffeine at least 30 minutes before their appointment.

Did you know?

Before a vaccine is licensed in the USA, the Food and Drug Administration (FDA) reviews it for safety and effectiveness. The CDC then reviews all studies again, as well as the American Academy of Pediatrics and the American Academy of Family Physicians. Every lot of vaccine is tested before administration to the public, and the FDA regularly inspects vaccine manufacturers' facilities.

Did you know?

Asthma attacks and symptoms usually get started by specific triggers (such as viruses, allergies, gases, and air particles). You should talk to your doctor about these triggers and find ways to avoid or get rid of them.

Did you know?

Many people have small pouches in their colons that bulge outward through weak spots. Each pouch is called a diverticulum. About 10% of Americans older than age 40 years have diverticulosis, which, when the pouches become infected or inflamed, is called diverticulitis. The main cause of diverticular disease is a low-fiber diet.

Did you know?

When taking monoamine oxidase inhibitors, people should avoid a variety of foods, which include alcoholic beverages, bean curd, broad (fava) bean pods, cheese, fish, ginseng, protein extracts, meat, sauerkraut, shrimp paste, soups, and yeast.

For a complete list of videos, visit our video library