The biggest challenge in planning large-scale systems development is scheduling. Describethe three approaches that organizations can take to address this challenge.
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

voltaire123

  • Sr. Member
  • ****
  • Posts: 301
Answer to Question 1

TRUE

Answer to Question 2

The first approach that organizations can take to address the challenge of scheduling
large-scale systems development projects is to avoid all major schedule risks by never
developing software in-house. Instead, they can license software from vendors. However, if no
suitable software exists, companies can take one of two remaining approaches. They can admit
the impossibility of systems development scheduling and plan accordingly. They can abandon
the systems development life cycle and decide to invest a certain level of resources into a project,
manage it as best as they can, and take the schedule that produces results. The third approach is
to attempt to schedule the development project in spite of all difficulties. Several different
estimation techniques can be used. If the project is similar to a past project, the schedule data
from that past project can be used for planning. When such similar past projects exist, this
technique can produce quality schedule estimates. If there is no such past project, managers can
estimate the number of lines of code that will need to be written. Then they can use industry or
company averages to estimate the time required. Another technique is to estimate the function
points in a program, use each function point to determine the number of lines of code, and use
that number to estimate schedules.




sheilaspns

  • Member
  • Posts: 567
Reply 2 on: Jul 7, 2018
Excellent


meganmoser117

  • Member
  • Posts: 303
Reply 3 on: Yesterday
Gracias!

 

Did you know?

Persons who overdose with cardiac glycosides have a better chance of overall survival if they can survive the first 24 hours after the overdose.

Did you know?

Illness; diuretics; laxative abuse; hot weather; exercise; sweating; caffeine; alcoholic beverages; starvation diets; inadequate carbohydrate consumption; and diets high in protein, salt, or fiber can cause people to become dehydrated.

Did you know?

Famous people who died from poisoning or drug overdose include, Adolf Hitler, Socrates, Juan Ponce de Leon, Marilyn Monroe, Judy Garland, and John Belushi.

Did you know?

More than 4.4billion prescriptions were dispensed within the United States in 2016.

Did you know?

Astigmatism is the most common vision problem. It may accompany nearsightedness or farsightedness. It is usually caused by an irregularly shaped cornea, but sometimes it is the result of an irregularly shaped lens. Either type can be corrected by eyeglasses, contact lenses, or refractive surgery.

For a complete list of videos, visit our video library