Author Question: To construct the Gantt chart, a ________ is drawn for each activity that reflects its sequence and ... (Read 80 times)

frankwu

  • Hero Member
  • *****
  • Posts: 549
To construct the Gantt chart, a ________ is drawn for each activity that reflects its sequence and duration.
 
  A) Horizontal line
  B) Horizontal bar
  C) Vertical line
  D) Vertical bar

Question 2

When a steering committee chooses a project it is referred as a bottom-up source.
 
  Indicate whether the statement is true or false


dellikani2015

  • Sr. Member
  • ****
  • Posts: 332
Answer to Question 1

B

Answer to Question 2

FALSE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Approximately 25% of all reported medication errors result from some kind of name confusion.

Did you know?

Certain topical medications such as clotrimazole and betamethasone are not approved for use in children younger than 12 years of age. They must be used very cautiously, as directed by a doctor, to treat any child. Children have a much greater response to topical steroid medications.

Did you know?

In the ancient and medieval periods, dysentery killed about ? of all babies before they reach 12 months of age. The disease was transferred through contaminated drinking water, because there was no way to adequately dispose of sewage, which contaminated the water.

Did you know?

If all the neurons in the human body were lined up, they would stretch more than 600 miles.

Did you know?

Approximately 15–25% of recognized pregnancies end in miscarriage. However, many miscarriages often occur before a woman even knows she is pregnant.

For a complete list of videos, visit our video library