Author Question: To review a project's tasks and their interrelationships, you would use a A) PERT chart. B) ... (Read 53 times)

audragclark

  • Hero Member
  • *****
  • Posts: 579
To review a project's tasks and their interrelationships, you would use a
 
  A) PERT chart.
  B) Gantt chart.
  C) either A or B.
  D) neither A nor B.

Question 2

Digital subscriber lines
 
  A) operate over existing telephone lines to carry voice, data, and video.
  B) operate over coaxial cable lines to deliver Internet access.
  C) are very-high-speed data lines typically leased from long-distance telephone companies.
  D) have up to twenty-four 64-Kbps channels.
  E) are assigned to every computer on the Internet.



mochi09

  • Sr. Member
  • ****
  • Posts: 335
Answer to Question 1

A

Answer to Question 2

A



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Atropine was named after the Greek goddess Atropos, the oldest and ugliest of the three sisters known as the Fates, who controlled the destiny of men.

Did you know?

A seasonal flu vaccine is the best way to reduce the chances you will get seasonal influenza and spread it to others.

Did you know?

In 1864, the first barbiturate (barbituric acid) was synthesized.

Did you know?

The modern decimal position system was the invention of the Hindus (around 800 AD), involving the placing of numerals to indicate their value (units, tens, hundreds, and so on).

Did you know?

The senior population grows every year. Seniors older than 65 years of age now comprise more than 13% of the total population. However, women outlive men. In the 85-and-over age group, there are only 45 men to every 100 women.

For a complete list of videos, visit our video library