Author Question: A critical path refers to: A) a sequence of task activities whose order and durations indirectly ... (Read 124 times)

Lobcity

  • Hero Member
  • *****
  • Posts: 524
A critical path refers to:
 
  A) a sequence of task activities whose order and durations indirectly affect the completion date of a project.
  B) a sequence of task activities whose order and durations directly affect the completion date of a project.
  C) a sequence of task activities whose order must be performed in parallel.
  D) a sequence of task activities whose duration cannot last more than 40 percent of the time allotted to the project.
  E) none of the above.

Question 2

Book, supplier, and state are examples of entity types.
 
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

fromAlphatoOmega22

  • Sr. Member
  • ****
  • Posts: 345
Answer to Question 1

B
Explanation: B) A critical path is a sequence of activities.

Answer to Question 2

TRUE
Explanation: An entity type is a collection of entities that share common properties or characteristics (i.e., book, supplier, and state).
CL




Lobcity

  • Member
  • Posts: 524
Reply 2 on: Jul 7, 2018
Great answer, keep it coming :)


Jsherida

  • Member
  • Posts: 314
Reply 3 on: Yesterday
Excellent

 

Did you know?

Although the Roman numeral for the number 4 has always been taught to have been "IV," according to historians, the ancient Romans probably used "IIII" most of the time. This is partially backed up by the fact that early grandfather clocks displayed IIII for the number 4 instead of IV. Early clockmakers apparently thought that the IIII balanced out the VIII (used for the number 8) on the clock face and that it just looked better.

Did you know?

There are actually 60 minerals, 16 vitamins, 12 essential amino acids, and three essential fatty acids that your body needs every day.

Did you know?

There can actually be a 25-hour time difference between certain locations in the world. The International Date Line passes between the islands of Samoa and American Samoa. It is not a straight line, but "zig-zags" around various island chains. Therefore, Samoa and nearby islands have one date, while American Samoa and nearby islands are one day behind. Daylight saving time is used in some islands, but not in others—further shifting the hours out of sync with natural time.

Did you know?

Each year in the United States, there are approximately six million pregnancies. This means that at any one time, about 4% of women in the United States are pregnant.

Did you know?

Approximately 70% of expectant mothers report experiencing some symptoms of morning sickness during the first trimester of pregnancy.

For a complete list of videos, visit our video library