A critical path refers to:
 
  A) a sequence of task activities whose order and durations indirectly affect the completion date of a project.
  B) a sequence of task activities whose order and durations directly affect the completion date of a project.
  C) a sequence of task activities whose order must be performed in parallel.
  D) a sequence of task activities whose duration cannot last more than 40 percent of the time allotted to the project.
  E) none of the above.

Question 2

Book, supplier, and state are examples of entity types.
 
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

fromAlphatoOmega22

  • Sr. Member
  • ****
  • Posts: 345
Answer to Question 1

B
Explanation: B) A critical path is a sequence of activities.

Answer to Question 2

TRUE
Explanation: An entity type is a collection of entities that share common properties or characteristics (i.e., book, supplier, and state).
CL




Lobcity

  • Member
  • Posts: 524
Reply 2 on: Jul 7, 2018
:D TYSM


TheNamesImani

  • Member
  • Posts: 334
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

Illicit drug use costs the United States approximately $181 billion every year.

Did you know?

People with high total cholesterol have about two times the risk for heart disease as people with ideal levels.

Did you know?

Though “Krazy Glue” or “Super Glue” has the ability to seal small wounds, it is not recommended for this purpose since it contains many substances that should not enter the body through the skin, and may be harmful.

Did you know?

Patients who have undergone chemotherapy for the treatment of cancer often complain of a lack of mental focus; memory loss; and a general diminution in abilities such as multitasking, attention span, and general mental agility.

Did you know?

Coca-Cola originally used coca leaves and caffeine from the African kola nut. It was advertised as a therapeutic agent and "pickerupper." Eventually, its formulation was changed, and the coca leaves were removed because of the effects of regulation on cocaine-related products.

For a complete list of videos, visit our video library