Author Question: Which of the following is the first step in materials requirements planning (MRP)? a. Setting ... (Read 70 times)

cmoore54

  • Hero Member
  • *****
  • Posts: 568
Which of the following is the first step in materials requirements planning (MRP)?
 
 

a. Setting deadlines for production and operations
  b. Specifying materials and parts needed for production and operations
  c. Determine inventory on hand
  d. Establish ordering and delivery schedules
  e. Rotate materials and parts to insure timely usage



Question 2

Materials Requirement Planning is valuable to managers because:
 
 

a. it is easily learned by all members of an organization.
  b. it can handle different lead times effectively.
  c. it does not require the use of a computer.
  d. All of these are reasons why MRP is valuable.
  e. None of these are reasons why MRP is valuable.




Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

fromAlphatoOmega22

  • Sr. Member
  • ****
  • Posts: 345
Answer to Question 1

B

Answer to Question 2

B




cmoore54

  • Member
  • Posts: 568
Reply 2 on: Jul 21, 2018
Wow, this really help


bimper21

  • Member
  • Posts: 309
Reply 3 on: Yesterday
Excellent

 

Did you know?

As many as 20% of Americans have been infected by the fungus known as Histoplasmosis. While most people are asymptomatic or only have slight symptoms, infection can progress to a rapid and potentially fatal superinfection.

Did you know?

Medication errors are three times higher among children and infants than with adults.

Did you know?

Fewer than 10% of babies are born on their exact due dates, 50% are born within 1 week of the due date, and 90% are born within 2 weeks of the date.

Did you know?

Pregnant women usually experience a heightened sense of smell beginning late in the first trimester. Some experts call this the body's way of protecting a pregnant woman from foods that are unsafe for the fetus.

Did you know?

The Food and Drug Administration has approved Risperdal, an adult antipsychotic drug, for the symptomatic treatment of irritability in children and adolescents with autism. The approval is the first for the use of a drug to treat behaviors associated with autism in children. These behaviors are included under the general heading of irritability and include aggression, deliberate self-injury, and temper tantrums.

For a complete list of videos, visit our video library