Which of the following is the first step in materials requirements planning (MRP)?
 
 

a. Setting deadlines for production and operations
  b. Specifying materials and parts needed for production and operations
  c. Determine inventory on hand
  d. Establish ordering and delivery schedules
  e. Rotate materials and parts to insure timely usage



Question 2

Materials Requirement Planning is valuable to managers because:
 
 

a. it is easily learned by all members of an organization.
  b. it can handle different lead times effectively.
  c. it does not require the use of a computer.
  d. All of these are reasons why MRP is valuable.
  e. None of these are reasons why MRP is valuable.




Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

fromAlphatoOmega22

  • Sr. Member
  • ****
  • Posts: 345
Answer to Question 1

B

Answer to Question 2

B




cmoore54

  • Member
  • Posts: 568
Reply 2 on: Jul 21, 2018
:D TYSM


mohan

  • Member
  • Posts: 362
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

When blood is deoxygenated and flowing back to the heart through the veins, it is dark reddish-blue in color. Blood in the arteries that is oxygenated and flowing out to the body is bright red. Whereas arterial blood comes out in spurts, venous blood flows.

Did you know?

Computer programs are available that crosscheck a new drug's possible trade name with all other trade names currently available. These programs detect dangerous similarities between names and alert the manufacturer of the drug.

Did you know?

A serious new warning has been established for pregnant women against taking ACE inhibitors during pregnancy. In the study, the risk of major birth defects in children whose mothers took ACE inhibitors during the first trimester was nearly three times higher than in children whose mothers didn't take ACE inhibitors. Physicians can prescribe alternative medications for pregnant women who have symptoms of high blood pressure.

Did you know?

Approximately one in four people diagnosed with diabetes will develop foot problems. Of these, about one-third will require lower extremity amputation.

Did you know?

There are 60,000 miles of blood vessels in every adult human.

For a complete list of videos, visit our video library