Why do air-handling units require field adjustment during the commissioning phase?
 
  A) The performance requirements of the blower cannot be determined in advance.
  B) Manufacturing errors that affect blower performance are common.
  C) To match the blower performance to the system requirements
  D) Air-handling units normally do not require field adjustment.

Question 2

Draining a small fraction of circulating water from the tower sump to prevent the buildup and concentration of scale forming minerals is called:
 
  A) Sump purging. B) Draindown. C) Blowdown. D) Desalinization.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

reversalruiz

  • Sr. Member
  • ****
  • Posts: 327
Answer to Question 1

C

Answer to Question 2

C




reversalruiz

  • Sr. Member
  • ****
  • Posts: 327

 

Did you know?

About 100 new prescription or over-the-counter drugs come into the U.S. market every year.

Did you know?

The eye muscles are the most active muscles in the whole body. The external muscles that move the eyes are the strongest muscles in the human body for the job they have to do. They are 100 times more powerful than they need to be.

Did you know?

Excessive alcohol use costs the country approximately $235 billion every year.

Did you know?

Most strokes are caused when blood clots move to a blood vessel in the brain and block blood flow to that area. Thrombolytic therapy can be used to dissolve the clot quickly. If given within 3 hours of the first stroke symptoms, this therapy can help limit stroke damage and disability.

Did you know?

Approximately 500,000 babies are born each year in the United States to teenage mothers.

For a complete list of videos, visit our video library