This topic contains a solution. Click here to go to the answer

Author Question: Give an example of how the but for schedule might be used in a contractor's claim for added ... (Read 79 times)

pepyto

  • Hero Member
  • *****
  • Posts: 547
Give an example of how the but for schedule might be used in a contractor's claim for added compensation.
 
  What will be an ideal response?

Question 2

In the Blackhawk case, what role did construction schedules play in deciding the merits of the delay claim? Describe briefly how the schedules were prepared.
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

phuda

  • Sr. Member
  • ****
  • Posts: 348
Answer to Question 1

It must first be recognized that the but for schedule is a more compelling tool
if the contractor maintained an updated schedule throughout the construction period. It is
all the more compelling if the updated schedule bears a close resemblance to the
originally developed schedule, at least up to the event or occurrence that compromised
the schedule. The but for schedule is a good way to show how the schedule would
probably have been followed had it not be for a particular event or occurrence. Support
the owner suspends work for some reason, pushing the construction effort into the rainy
season. The but for schedule would essentially consist of the updated schedule with the
deletion of the owner's suspension of the work. In addition to the suspension period, the
schedule would show the added construction time (reduced productivity) that was
required as a result of performing work during the rainy season.

Answer to Question 2

As planned and as built CPM schedules were prepared after the project was
constructed. These were after-the-fact schedules developed by an independent -
consultant. Basing the information to be included in the schedule primarily on the
contractor's daily work logs, the consultant developed a schedule that was acceptable to
the Board of Contract Appeals. The Board acknowledged that the CPM schedule was
prepared well after events took place, but under close scrutiny of the Board, the schedule
was found to be acceptable. It is inferred, in this case, that the CPM schedule was critical
to the decision made by the Board.





 

Did you know?

In inpatient settings, adverse drug events account for an estimated one in three of all hospital adverse events. They affect approximately 2 million hospital stays every year, and prolong hospital stays by between one and five days.

Did you know?

For high blood pressure (hypertension), a new class of drug, called a vasopeptidase blocker (inhibitor), has been developed. It decreases blood pressure by simultaneously dilating the peripheral arteries and increasing the body's loss of salt.

Did you know?

Approximately 500,000 babies are born each year in the United States to teenage mothers.

Did you know?

HIV testing reach is still limited. An estimated 40% of people with HIV (more than 14 million) remain undiagnosed and do not know their infection status.

Did you know?

Astigmatism is the most common vision problem. It may accompany nearsightedness or farsightedness. It is usually caused by an irregularly shaped cornea, but sometimes it is the result of an irregularly shaped lens. Either type can be corrected by eyeglasses, contact lenses, or refractive surgery.

For a complete list of videos, visit our video library