Author Question: Give an example of how the but for schedule might be used in a contractor's claim for added ... (Read 80 times)

pepyto

  • Hero Member
  • *****
  • Posts: 547
Give an example of how the but for schedule might be used in a contractor's claim for added compensation.
 
  What will be an ideal response?

Question 2

In the Blackhawk case, what role did construction schedules play in deciding the merits of the delay claim? Describe briefly how the schedules were prepared.
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

phuda

  • Sr. Member
  • ****
  • Posts: 348
Answer to Question 1

It must first be recognized that the but for schedule is a more compelling tool
if the contractor maintained an updated schedule throughout the construction period. It is
all the more compelling if the updated schedule bears a close resemblance to the
originally developed schedule, at least up to the event or occurrence that compromised
the schedule. The but for schedule is a good way to show how the schedule would
probably have been followed had it not be for a particular event or occurrence. Support
the owner suspends work for some reason, pushing the construction effort into the rainy
season. The but for schedule would essentially consist of the updated schedule with the
deletion of the owner's suspension of the work. In addition to the suspension period, the
schedule would show the added construction time (reduced productivity) that was
required as a result of performing work during the rainy season.

Answer to Question 2

As planned and as built CPM schedules were prepared after the project was
constructed. These were after-the-fact schedules developed by an independent -
consultant. Basing the information to be included in the schedule primarily on the
contractor's daily work logs, the consultant developed a schedule that was acceptable to
the Board of Contract Appeals. The Board acknowledged that the CPM schedule was
prepared well after events took place, but under close scrutiny of the Board, the schedule
was found to be acceptable. It is inferred, in this case, that the CPM schedule was critical
to the decision made by the Board.





 

Did you know?

Adults are resistant to the bacterium that causes Botulism. These bacteria thrive in honey – therefore, honey should never be given to infants since their immune systems are not yet resistant.

Did you know?

There are more nerve cells in one human brain than there are stars in the Milky Way.

Did you know?

One way to reduce acid reflux is to lose two or three pounds. Most people lose weight in the belly area first when they increase exercise, meaning that heartburn can be reduced quickly by this method.

Did you know?

The U.S. Preventive Services Task Force recommends that all women age 65 years of age or older should be screened with bone densitometry.

Did you know?

Illicit drug use costs the United States approximately $181 billion every year.

For a complete list of videos, visit our video library