Author Question: The longest path through a PERT diagram is referred to as the ________ path. A) critical B) ... (Read 155 times)

jace

  • Hero Member
  • *****
  • Posts: 541
The longest path through a PERT diagram is referred to as the ________ path.
 
  A) critical
  B) hardest
  C) fastest
  D) slowest

Question 2

A BPM process category is people-intensive processes.
 
  Indicate whether the statement is true or false



Briannahope

  • Sr. Member
  • ****
  • Posts: 364
Answer to Question 1

A

Answer to Question 2

TRUE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The FDA recognizes 118 routes of administration.

Did you know?

Between 1999 and 2012, American adults with high total cholesterol decreased from 18.3% to 12.9%

Did you know?

More than 34,000 trademarked medication names and more than 10,000 generic medication names are in use in the United States.

Did you know?

The average person is easily confused by the terms pharmaceutics and pharmacology, thinking they are one and the same. Whereas pharmaceutics is the science of preparing and dispensing drugs (otherwise known as the science of pharmacy), pharmacology is the study of medications.

Did you know?

Cytomegalovirus affects nearly the same amount of newborns every year as Down syndrome.

For a complete list of videos, visit our video library