Author Question: Actual measurements for construction are taken from the _____. a. primary control points b. ... (Read 52 times)

appyboo

  • Hero Member
  • *****
  • Posts: 527
Actual measurements for construction are taken from the _____.
 
  a. primary control points
  b. secondary control points
  c. subsidiary control points
  d. working control points

Question 2

The location and levelness of concrete forms are established by using _____.
 
  a. azimuth stakes
  b. control centers
  c. elevation posts
  d. control points



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

ryrychapman11

  • Sr. Member
  • ****
  • Posts: 334
Answer to Question 1

d

Answer to Question 2

d




ryrychapman11

  • Sr. Member
  • ****
  • Posts: 334

 

Did you know?

When blood is exposed to air, it clots. Heparin allows the blood to come in direct contact with air without clotting.

Did you know?

In 1864, the first barbiturate (barbituric acid) was synthesized.

Did you know?

Adult head lice are gray, about ? inch long, and often have a tiny dot on their backs. A female can lay between 50 and 150 eggs within the several weeks that she is alive. They feed on human blood.

Did you know?

Liver spots have nothing whatsoever to do with the liver. They are a type of freckles commonly seen in older adults who have been out in the sun without sufficient sunscreen.

Did you know?

It is important to read food labels and choose foods with low cholesterol and saturated trans fat. You should limit saturated fat to no higher than 6% of daily calories.

For a complete list of videos, visit our video library