Author Question: Give an example of how the but for schedule might be used in a contractor's claim for added ... (Read 104 times)

pepyto

  • Hero Member
  • *****
  • Posts: 547
Give an example of how the but for schedule might be used in a contractor's claim for added compensation.
 
  What will be an ideal response?

Question 2

In the Blackhawk case, what role did construction schedules play in deciding the merits of the delay claim? Describe briefly how the schedules were prepared.
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

phuda

  • Sr. Member
  • ****
  • Posts: 348
Answer to Question 1

It must first be recognized that the but for schedule is a more compelling tool
if the contractor maintained an updated schedule throughout the construction period. It is
all the more compelling if the updated schedule bears a close resemblance to the
originally developed schedule, at least up to the event or occurrence that compromised
the schedule. The but for schedule is a good way to show how the schedule would
probably have been followed had it not be for a particular event or occurrence. Support
the owner suspends work for some reason, pushing the construction effort into the rainy
season. The but for schedule would essentially consist of the updated schedule with the
deletion of the owner's suspension of the work. In addition to the suspension period, the
schedule would show the added construction time (reduced productivity) that was
required as a result of performing work during the rainy season.

Answer to Question 2

As planned and as built CPM schedules were prepared after the project was
constructed. These were after-the-fact schedules developed by an independent -
consultant. Basing the information to be included in the schedule primarily on the
contractor's daily work logs, the consultant developed a schedule that was acceptable to
the Board of Contract Appeals. The Board acknowledged that the CPM schedule was
prepared well after events took place, but under close scrutiny of the Board, the schedule
was found to be acceptable. It is inferred, in this case, that the CPM schedule was critical
to the decision made by the Board.





 

Did you know?

Drug-induced pharmacodynamic effects manifested in older adults include drug-induced renal toxicity, which can be a major factor when these adults are experiencing other kidney problems.

Did you know?

To prove that stomach ulcers were caused by bacteria and not by stress, a researcher consumed an entire laboratory beaker full of bacterial culture. After this, he did indeed develop stomach ulcers, and won the Nobel Prize for his discovery.

Did you know?

Acetaminophen (Tylenol) in overdose can seriously damage the liver. It should never be taken by people who use alcohol heavily; it can result in severe liver damage and even a condition requiring a liver transplant.

Did you know?

Always store hazardous household chemicals in their original containers out of reach of children. These include bleach, paint, strippers and products containing turpentine, garden chemicals, oven cleaners, fondue fuels, nail polish, and nail polish remover.

Did you know?

Amoebae are the simplest type of protozoans, and are characterized by a feeding and dividing trophozoite stage that moves by temporary extensions called pseudopodia or false feet.

For a complete list of videos, visit our video library