A PERT diagram is useful when:
 
  A) activities can be done in parallel rather than sequence.
  B) there is no slack time available.
  C) the project team needs to know which activities should be done at which point in time.
  D) activities do not have any precedent activities.

Question 2

Within one relation, two rows can be identical.
 
  Indicate whether the statement is true or false



debra928

  • Sr. Member
  • ****
  • Posts: 342
Answer to Question 1

A

Answer to Question 2

FALSE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The first-known contraceptive was crocodile dung, used in Egypt in 2000 BC. Condoms were also reportedly used, made of animal bladders or intestines.

Did you know?

The first successful kidney transplant was performed in 1954 and occurred in Boston. A kidney from an identical twin was transplanted into his dying brother's body and was not rejected because it did not appear foreign to his body.

Did you know?

Methicillin-resistant Staphylococcus aureus or MRSA was discovered in 1961 in the United Kingdom. It if often referred to as a superbug. MRSA infections cause more deaths in the United States every year than AIDS.

Methicilli ...
Did you know?

HIV testing reach is still limited. An estimated 40% of people with HIV (more than 14 million) remain undiagnosed and do not know their infection status.

Did you know?

Historic treatments for rheumatoid arthritis have included gold salts, acupuncture, a diet consisting of apples or rhubarb, nutmeg, nettles, bee venom, bracelets made of copper, prayer, rest, tooth extractions, fasting, honey, vitamins, insulin, snow collected on Christmas, magnets, and electric convulsion therapy.

For a complete list of videos, visit our video library