Author Question: A PERT diagram is useful when: A) activities can be done in parallel rather than sequence. B) ... (Read 60 times)

haleyc112

  • Hero Member
  • *****
  • Posts: 600
A PERT diagram is useful when:
 
  A) activities can be done in parallel rather than sequence.
  B) there is no slack time available.
  C) the project team needs to know which activities should be done at which point in time.
  D) activities do not have any precedent activities.

Question 2

Within one relation, two rows can be identical.
 
  Indicate whether the statement is true or false



debra928

  • Sr. Member
  • ****
  • Posts: 342
Answer to Question 1

A

Answer to Question 2

FALSE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Long-term mental and physical effects from substance abuse include: paranoia, psychosis, immune deficiencies, and organ damage.

Did you know?

Giardia is one of the most common intestinal parasites worldwide, and infects up to 20% of the world population, mostly in poorer countries with inadequate sanitation. Infections are most common in children, though chronic Giardia is more common in adults.

Did you know?

Vampire bats have a natural anticoagulant in their saliva that permits continuous bleeding after they painlessly open a wound with their incisors. This capillary blood does not cause any significant blood loss to their victims.

Did you know?

Many medications that are used to treat infertility are injected subcutaneously. This is easy to do using the anterior abdomen as the site of injection but avoiding the area directly around the belly button.

Did you know?

Atropine was named after the Greek goddess Atropos, the oldest and ugliest of the three sisters known as the Fates, who controlled the destiny of men.

For a complete list of videos, visit our video library