A PERT diagram is useful when:
 
  A) activities can be done in parallel rather than sequence.
  B) there is no slack time available.
  C) the project team needs to know which activities should be done at which point in time.
  D) activities do not have any precedent activities.

Question 2

Within one relation, two rows can be identical.
 
  Indicate whether the statement is true or false



debra928

  • Sr. Member
  • ****
  • Posts: 342
Answer to Question 1

A

Answer to Question 2

FALSE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The average older adult in the United States takes five prescription drugs per day. Half of these drugs contain a sedative. Alcohol should therefore be avoided by most senior citizens because of the dangerous interactions between alcohol and sedatives.

Did you know?

After a vasectomy, it takes about 12 ejaculations to clear out sperm that were already beyond the blocked area.

Did you know?

Human kidneys will clean about 1 million gallons of blood in an average lifetime.

Did you know?

Patients who have been on total parenteral nutrition for more than a few days may need to have foods gradually reintroduced to give the digestive tract time to start working again.

Did you know?

Intradermal injections are somewhat difficult to correctly administer because the skin layers are so thin that it is easy to accidentally punch through to the deeper subcutaneous layer.

For a complete list of videos, visit our video library