A PERT diagram is useful when:
 
  A) activities can be done in parallel rather than sequence.
  B) there is no slack time available.
  C) the project team needs to know which activities should be done at which point in time.
  D) activities do not have any precedent activities.

Question 2

Within one relation, two rows can be identical.
 
  Indicate whether the statement is true or false



debra928

  • Sr. Member
  • ****
  • Posts: 342
Answer to Question 1

A

Answer to Question 2

FALSE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Egg cells are about the size of a grain of sand. They are formed inside of a female's ovaries before she is even born.

Did you know?

There are more sensory neurons in the tongue than in any other part of the body.

Did you know?

In 2012, nearly 24 milliion Americans, aged 12 and older, had abused an illicit drug, according to the National Institute on Drug Abuse (NIDA).

Did you know?

People often find it difficult to accept the idea that bacteria can be beneficial and improve health. Lactic acid bacteria are good, and when eaten, these bacteria improve health and increase longevity. These bacteria included in foods such as yogurt.

Did you know?

On average, the stomach produces 2 L of hydrochloric acid per day.

For a complete list of videos, visit our video library