Author Question: The type of schedule that shows dependent and critical path activities is the _____. a. Gantt ... (Read 49 times)

anshika

  • Hero Member
  • *****
  • Posts: 510
The type of schedule that shows dependent and critical path activities is the _____.
 
  a. Gantt chart
  b. network schedule
  c. bar chart
  d. time and materials schedule

Question 2

An example of a non-monetary award recognizing hard work is _____.
 
  a. a holiday bonus
  b. paid time off
  c. a salary increase
  d. a company jacket



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

ladyjames123

  • Sr. Member
  • ****
  • Posts: 346
Answer to Question 1

b

Answer to Question 2

d




anshika

  • Member
  • Posts: 510
Reply 2 on: Jul 24, 2018
:D TYSM


rachel

  • Member
  • Posts: 323
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

Many medications that are used to treat infertility are injected subcutaneously. This is easy to do using the anterior abdomen as the site of injection but avoiding the area directly around the belly button.

Did you know?

Throughout history, plants containing cardiac steroids have been used as heart drugs and as poisons (e.g., in arrows used in combat), emetics, and diuretics.

Did you know?

The FDA recognizes 118 routes of administration.

Did you know?

Today, nearly 8 out of 10 pregnant women living with HIV (about 1.1 million), receive antiretrovirals.

Did you know?

The strongest synthetic topical retinoid drug available, tazarotene, is used to treat sun-damaged skin, acne, and psoriasis.

For a complete list of videos, visit our video library