The type of schedule that shows dependent and critical path activities is the _____.
 
  a. Gantt chart
  b. network schedule
  c. bar chart
  d. time and materials schedule

Question 2

An example of a non-monetary award recognizing hard work is _____.
 
  a. a holiday bonus
  b. paid time off
  c. a salary increase
  d. a company jacket



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

ladyjames123

  • Sr. Member
  • ****
  • Posts: 346
Answer to Question 1

b

Answer to Question 2

d




anshika

  • Member
  • Posts: 510
Reply 2 on: Jul 24, 2018
YES! Correct, THANKS for helping me on my review


Dominic

  • Member
  • Posts: 328
Reply 3 on: Yesterday
Gracias!

 

Did you know?

One way to reduce acid reflux is to lose two or three pounds. Most people lose weight in the belly area first when they increase exercise, meaning that heartburn can be reduced quickly by this method.

Did you know?

People about to have surgery must tell their health care providers about all supplements they take.

Did you know?

Children of people with alcoholism are more inclined to drink alcohol or use hard drugs. In fact, they are 400 times more likely to use hard drugs than those who do not have a family history of alcohol addiction.

Did you know?

Elderly adults are living longer, and causes of death are shifting. At the same time, autopsy rates are at or near their lowest in history.

Did you know?

The word drug comes from the Dutch word droog (meaning "dry"). For centuries, most drugs came from dried plants, hence the name.

For a complete list of videos, visit our video library