Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 999 times)

Deast7027

  • Hero Member
  • *****
  • Posts: 538
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using three processors.


◦ This timeline is an illegal schedule because task F was started before task E was completed.
◦ This timeline is an illegal schedule because task E was started before task C was completed.
◦ This timeline is not an optimal schedule because the project can be scheduled with a finishing time of 11 hours.
◦ This timeline is an optimal schedule for three processors.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

Loise Hard

  • Sr. Member
  • ****
  • Posts: 340
This timeline is an illegal schedule because task F was started before task E was completed.



sjones

  • Hero Member
  • *****
  • Posts: 520
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using three processors.


◦ This timeline is not optimal because task F was started after processor 3 was idle for 2 hours.
◦ This timeline is not an optimal schedule because the project can be scheduled with a finishing time of 12 hours.
◦ This timeline is an illegal schedule because task E was started before task C was completed.
◦ This timeline is an optimal schedule for three processors.
◦ none of these



jomama

  • Sr. Member
  • ****
  • Posts: 346
This timeline is an optimal schedule for three processors.



jhjkgdfhk

  • Hero Member
  • *****
  • Posts: 569
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an optimal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This is the timeline one gets using the critical-path algorithm.
◦ This timeline is an illegal schedule.
◦ none of these



djpooyouma

  • Sr. Member
  • ****
  • Posts: 325
This is the timeline one gets using the decreasing-time algorithm.



mydiamond

  • Hero Member
  • *****
  • Posts: 804
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an illegal schedule.
◦ This timeline is an optimal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This is the timeline one gets using the critical-path algorithm.
◦ none of these



Joy Chen

  • Sr. Member
  • ****
  • Posts: 354
This timeline is an illegal schedule.



bio_gurl

  • Hero Member
  • *****
  • Posts: 524
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an optimal schedule.
◦ This timeline is an illegal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This is the timeline one gets using the critical-path algorithm.
◦ none of these



frre432

  • Sr. Member
  • ****
  • Posts: 347
This is the timeline one gets using the critical-path algorithm.



 

Did you know?

Increased intake of vitamin D has been shown to reduce fractures up to 25% in older people.

Did you know?

Cancer has been around as long as humankind, but only in the second half of the twentieth century did the number of cancer cases explode.

Did you know?

Your heart beats over 36 million times a year.

Did you know?

Multiple sclerosis is a condition wherein the body's nervous system is weakened by an autoimmune reaction that attacks the myelin sheaths of neurons.

Did you know?

According to the FDA, adverse drug events harmed or killed approximately 1,200,000 people in the United States in the year 2015.

For a complete list of videos, visit our video library