Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using three processors.


◦ This timeline is an illegal schedule because task F was started before task E was completed.
◦ This timeline is an illegal schedule because task E was started before task C was completed.
◦ This timeline is not an optimal schedule because the project can be scheduled with a finishing time of 11 hours.
◦ This timeline is an optimal schedule for three processors.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

Loise Hard

  • Sr. Member
  • ****
  • Posts: 340
This timeline is an illegal schedule because task F was started before task E was completed.



sjones

  • Hero Member
  • *****
  • Posts: 520
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using three processors.


◦ This timeline is not optimal because task F was started after processor 3 was idle for 2 hours.
◦ This timeline is not an optimal schedule because the project can be scheduled with a finishing time of 12 hours.
◦ This timeline is an illegal schedule because task E was started before task C was completed.
◦ This timeline is an optimal schedule for three processors.
◦ none of these



jomama

  • Sr. Member
  • ****
  • Posts: 346
This timeline is an optimal schedule for three processors.



jhjkgdfhk

  • Hero Member
  • *****
  • Posts: 569
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an optimal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This is the timeline one gets using the critical-path algorithm.
◦ This timeline is an illegal schedule.
◦ none of these



djpooyouma

  • Sr. Member
  • ****
  • Posts: 325
This is the timeline one gets using the decreasing-time algorithm.



mydiamond

  • Hero Member
  • *****
  • Posts: 804
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an illegal schedule.
◦ This timeline is an optimal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This is the timeline one gets using the critical-path algorithm.
◦ none of these



Joy Chen

  • Sr. Member
  • ****
  • Posts: 354
This timeline is an illegal schedule.



bio_gurl

  • Hero Member
  • *****
  • Posts: 524
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Consider the following timeline using two processors.


◦ This timeline is an optimal schedule.
◦ This timeline is an illegal schedule.
◦ This is the timeline one gets using the decreasing-time algorithm.
◦ This is the timeline one gets using the critical-path algorithm.
◦ none of these



frre432

  • Sr. Member
  • ****
  • Posts: 347
This is the timeline one gets using the critical-path algorithm.



 

Did you know?

Methicillin-resistant Staphylococcus aureus or MRSA was discovered in 1961 in the United Kingdom. It if often referred to as a superbug. MRSA infections cause more deaths in the United States every year than AIDS.

Methicilli ...
Did you know?

It is widely believed that giving a daily oral dose of aspirin to heart attack patients improves their chances of survival because the aspirin blocks the formation of new blood clots.

Did you know?

For high blood pressure (hypertension), a new class of drug, called a vasopeptidase blocker (inhibitor), has been developed. It decreases blood pressure by simultaneously dilating the peripheral arteries and increasing the body's loss of salt.

Did you know?

Dogs have been used in studies to detect various cancers in human subjects. They have been trained to sniff breath samples from humans that were collected by having them breathe into special tubes. These people included 55 lung cancer patients, 31 breast cancer patients, and 83 cancer-free patients. The dogs detected 54 of the 55 lung cancer patients as having cancer, detected 28 of the 31 breast cancer patients, and gave only three false-positive results (detecting cancer in people who didn't have it).

Did you know?

Cocaine was isolated in 1860 and first used as a local anesthetic in 1884. Its first clinical use was by Sigmund Freud to wean a patient from morphine addiction. The fictional character Sherlock Holmes was supposed to be addicted to cocaine by injection.

For a complete list of videos, visit our video library